Standard Processes¶
[this section needs cleaning up]
We’d like the minimum process necessary. It should be clear why any process we have is required because of the principles.
The SRU team should strive for consistency. No moving goalposts. Good communication needed usually through documentation. Cannot expect consistency if something has always been done without documentation by one SRU team member.
Any deviance from the ideal SRU must be called out and justified
Anticipate our questions. If we ask questions, try to anticipate them next time!
We would prefer for users affected to do the verification that the bug is fixed, and for many people to verify that the change didn’t regress their use cases. However in practice it is difficult to find people to do SRU verification. As long as the agreed Test Plan is followed we will accept verification reports from anyone, including the person driving the SRU. Additional feedback of any form is also welcome; that doesn’t need to follow the Test Plan. But one verification that followed the Test Plan is the minimum requirement for an SRU to be released. Note that we require that the package as built in -proposed be tested, and verifications should include evidence that this has happened (typically by including the version number of the package tested).
No iterating in stable releases. [Robie needs to explain what he means here]
Autopkgtest failures¶
Packages accepted into -proposed as per the SRU process automatically trigger related autopkgtests, similarly to how it happens for the development series. Once those tests are finished, the pending SRU page provides links to any failures that have been noticed for the selected upload. The responsibility of the SRU driver (and/or the person performing update verification) is to make sure the upload does not cause any regressions—both in manual and automated testing.
In the case where an SRU upload triggers an autopkgtest regression, the target package will not be released into -updates until the failure is resolved. There are a few ways that can happen:
If the reported autopkgtest regression is a real regression caused by the upload, the update should be considered verification-failed and the package should be re-uploaded with the regression fixed. Otherwise the update will be removed from -proposed as per the usual procedures.
If the reported autopkgtest regression is not a real regression or not a regression caused by the proposed update (but instead broken by some other dependency), the analysis of this has to be documented for the SRU team. The generally recommended way is commenting on one of the SRU bugs for the upload. Once the rationale is submitted and approved/validated by an SRU member, the SRU team will add a badtest or reset-test hint for the broken package and release the update as per usual procedures (once validation and ageing is complete). Alternatively, the uploader/verifier can modify the hints and provide an MP in the bug along with the rationale. Useful input here can be re-running the failing test against only the release/updates pocket, as documented in the Proposed Migration wiki page.
If the reported autopkgtest regression is the result of a flaky test, the uploader can try re-running the test to see if it is indeed just a transient issue. If the issue still persists but the analysis clearly shows that it is not a real regression, a rationale for that should be provided in one of the SRU bugs.
It is important to remember that firstly it is the uploader’s responsibility to make sure the package is in a releasable state and that all the autopkgtests triggered by the upload are either passing or badtested. Of course, it is not the uploader’s responsibility to provide the hints for badtests themselves, but it is it’s responsibility to perform the analysis and verification of each listed regression.
Expected resolution for reported autopkgtest failures¶
If an SRU did not cause a regression, the update is intended to land but autopkgtest regressions are still found, then the possible resolutions for this situation are as follows:
An SRU must not be released if outstanding autopkgtest regressions are reported on the Pending SRU Report.
Ideally regressions can be fixed with new uploads to the proposed pockets as required. Fixes for autopkgtests are generally always acceptable. However uploads providing only test fixes will generally be staged using block-proposed-<series> (in which case they need a bug reference).
A regression not caused by the SRU may be badtest or reset-tested away (doesn’t matter which for SRUs).
See also: How-to → Handle an autopkgtest failure.
Phasing¶
Once a package is released to -updates, the update is then phased so that the update is gradually made available to expanding subsets of Ubuntu users. This process allows us to automatically monitor for regressions and halt the update process if any are found. Complete details about the process can be found in a blog post by Brian Murray.
The Phased-Update-Percentage is initially set to 10%, then a job is run (every 6 hours) that checks for regressions and if none are found the phased update percentage will be incremented by 10%. So an update will become fully phased after 54 hours or about 2 days. In the event that a regression is detected the Phased-Update-Percentage will be set to 0% thereby causing supported package managers (update-manager) not to install the update.
The progress of phased updates is visible in a report which is updated by the same job that does the phasing.
See also:
Regressions¶
See also: How-to → Handling regressions for the playbook to follow when a regression is reported
The SRU team drives the process that handles regressions reported against the updates pocket. Regressions that have taken place elsewhere (e.g. during a release upgrade, in the security pocket, in the proposed pocket or in Pro-specific repositories) are out of scope of this section.
Once a regression is confirmed, usually we have two choices to resolve it and we are under time pressure to do so:
Release an exact revert (“revert”).
Analyse the reason for the regression and try to amend the regressing update to fix that (“pushing ahead”).
By definition, a regression occurs as a failure in quality of the original fix together with a failure of QA (“failing factors”). Pushing ahead under time pressure is unlikely to resolve either of these issues, so we risk further regression by doing so.
Therefore, the SRU team takes the position that pushing ahead must not take place until the failing factors have been addressed and mitigations reviewed and approved without time pressure, and therefore in the general case our immediate and expected action shall be to revert instead. As a policy position, we will not waste time considering pushing ahead, unless one of the exceptions below applies.
Exceptions that justify pushing ahead¶
There is a known technical reason that a revert will fail (i.e. not work or cause a further issue), or that an SRU team member considers the risk of the revert failing to be too high.
The regression has been published in the updates pocket for long enough that the cost/benefit trade-off of a revert has diminished compared to users who are enjoying the fix.
There is some other good reason, in the opinion of an SRU team member, that has not been considered by this policy.
Responsibilities¶
It is expected that the SRU Driver will be available and take all non-SRU-privileged actions in handling the regression, under the direction of a decision-making SRU team member.
See also: Explanation → Role expectations
Phases¶
Regression reports must be triaged like any other. When a regression is first reported, we are uncertain if it is valid, and even if we are sure it is valid, we are unsure if it warrants action. Taking a clear position on our collective opinion on whether or not action is warranted is vital, and prevents confusion. Therefore, we define the following phases:
Uncertainty phase: there is a report of a regression, but we are not sure if it is valid.
Alert phase: in the opinion of an SRU team member, there is a credible report of a regression that warrants further investigation.
Action phase: an SRU team member has considered the available information, taken the decision that action is warranted, and communicated this decision.